Solar PV/Adams Parking Improvements

Project Scope:

pmReportData: scope
 New construction of a 1 MW (megawatt) solar photovoltaic canopy system in the Adams Parking Lot. In addition this project includes the installation of an electrical substation and completion of underground electrical "loop".
 

Project Status:

pmReportData: statusRemarks
Construction complete and electrical connection is on schedule. The campus powered up the solar PV panels on July 22, 2016. The substation and electrical loop is ongoing and construction should be completed in November 2016.

Architect:

pmReportData: architect
Power Engineering Services Inc.

Construction Manager:

pmReportData: constructionManager
Power Engineering Services

Contractor:

pmReportData: contractor
SunPower Corp Systems

 

 MeasureMLogo.png

Project Timeline:

pmReportData: startDate
June 2015
pmReportData: finishDate
June 2016

Status:

pmReportData: phase
Completed